Built on a rooftop

News
Built on a rooftop
Built on a rooftop
Since August 2026, uptown batterytogrid’s battery energy storage system (BESS) has been in operation. It is a battery-to-grid system: connected to the national grid via the campus’s own substation and Primeo’s power lines, the battery helps Swissgrid keep the grid stable. Yves Imoberdorf, CEO of uptown batterytogrid, explains how the system came about – and why it stands where you would hardly expect it

Cabinets instead of containers

The batteries sit on the roof of the converted substation. Because the system had to be modular, it does not use the usual large shipping containers but battery cabinets, each holding eight battery packs. A noise barrier surrounds the system, and from the outside it is practically invisible.

A system like this on a roof is unusual. A great deal therefore had to be clarified on the construction side, above all with the structural engineer, who had already worked on Buildings 1 and 8 on the site. His expertise was central to the whole concept, “because we decided to build the system on a roof – who does that?”

6 megawatts, 15 megawatt hours

The system has an output of 6 megawatts and stores 15 megawatt hours. Was the size a technical or an economic decision? “It was certainly both,” says Yves Imoberdorf. The team deliberately started with a smaller system: because of the space available, and because the size depends on what you want to do with the battery. On top of that, it is the first battery storage system of its own on the campus.

‍

The battery system on the roof of the substation during installation, March 2026.
The battery system on the roof of the substation during installation, March 2026.

Two partners, clear roles

Hitachi Energy supplied the entire battery system. Primeo manages the battery and markets its capacity to Swissgrid. For Yves Imoberdorf, the choice of these two partners was decisive: both are the right experts in their field, and that shows in the quality. Precisely because there was no standard solution for a system of this kind, the partners’ experience was particularly important.

The approval process also differed from that of an ordinary building project. Because this is a heavy-current installation, the responsible authority is not the usual cantonal office but the Federal Inspectorate for Heavy Current Installations (ESTI). “Of course there were a few follow-up questions, but it wasn’t as if we got stuck anywhere.” Overall, he says, the project went surprisingly smoothly, partly because Primeo already knew what mattered.

Uncharted territory

In the end, the hardest part was the technology itself, because so many variables interact.

There were many questions with no off-the-shelf answer.

Yves Imoberdorf
Yves Imoberdorf
CEO uptown batterytogrid

Some questions were discussed in groups of eight to ten people until a solution was found. That is exactly what drove the people involved, says Yves Imoberdorf: uncharted territory attracts people who want to develop. For him, that fits the campus. At uptownBasel, innovation does not stop at the computers; it extends into the infrastructure, all the way to the battery on the roof.

More news

Further reading from uptownBasel

Energy that thinks for itself
Energy
Campus
26.08.2026

Energy that thinks for itself

Read article
uptownBasel receives the SNBS-Areal pre-certificate
Energy
Campus
09.11.2026

uptownBasel receives the SNBS-Areal pre-certificate

Read article